How to read a work-in-progress (WIP) report

A WIP report shows whether your open jobs are billed ahead of or behind the work completed. Here is how to read one, line by line.

A work-in-progress report, or WIP schedule, lists every open job and compares how much work is done with how much has been billed. Banks and bonding companies ask for it. It is also one of the most useful reports an owner can read.

The columns

Each open job gets one row. The usual columns are:

  • Contract amount. The original contract plus approved change orders.
  • Estimated total cost. What you now expect the whole job to cost.
  • Cost to date. What has been spent so far.
  • Percent complete. Cost to date divided by estimated total cost.
  • Earned revenue. Percent complete multiplied by the contract amount.
  • Billed to date. What you have invoiced.
  • Over or under billing. Billed to date minus earned revenue.

A short example

A job has a $100,000 contract and an estimated cost of $80,000. So far you have spent $40,000 and billed $60,000.

  • Percent complete: $40,000 divided by $80,000 is 50 percent.
  • Earned revenue: 50 percent of $100,000 is $50,000.
  • Over billing: $60,000 billed minus $50,000 earned is $10,000.

You have billed $10,000 more than you have earned. That is good for cash today, but it is money you still owe work for.

What the numbers tell you

Over billed means you have collected ahead of the work. A little is healthy. A lot can mean trouble later, when the job needs cash that has already been spent elsewhere.

Under billed means you have done work you have not invoiced. It can point to slow billing, unapproved change orders, or a job running over its estimate.

The number that matters most

The report is only as good as the estimated total cost. If a job is going to run over and the estimate is not updated, the job will look more complete and more profitable than it is. Review estimates on open jobs every month, and update them when you learn something new.

What you need to build one

You need job costing in your books, current contract values including change orders, and an honest updated estimate for each open job. With those three, the report is simple arithmetic.

Updated . This guide is general information, not tax or legal advice for your situation.